Harrow View East, London

Developer

Barratt London

Project

Harrow View East, block F, London

Work undertaken

Design, supply, installation and commissioning of a smoke control system made up of four mechanical cores and a mechanical extraction system at basement level plus an F1 fire alarm serving all cores.

Equipment used

Zonal control panel, MCPs, 0.6m2 smoke dampers, pressure sensors, LED indication panel, smoke extraction fans and a 0.6m2 roof ventilator for air inlet to all cores.

Comfort ventilation was included – thermostats every four levels, a wind and rain sensor plus a smoke extraction fan at 20% duty.

Project duration

Four months from start to finish.